On January 16, 2025, FERC approved a contested settlement agreement and rate schedule governing the provision of reliability must-run (“RMR”) service from the Indian River Unit 4 generating facility (“Unit 4”) in PJM...more
On September 10, 2024, FERC issued an Order denying two complaints. The first complaint was filed on January 23, 2023 by Montana-Dakota Utilities Company (“MDU”) against Midcontinent Independent System Operator, Inc....more
On July 19, 2024, the United States Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) issued an Order denying Tenaska Clear Creek Wind, LLC’s (“Clear Creek”) challenges to FERC’s orders allowing the...more
On May 23, 2024, FERC issued an Order denying Lackawanna Energy Center LLC’s (“Lackawanna”) complaint against PJM Interconnection, L.L.C. (“PJM”) alleging that PJM failed to reimburse Lackawanna for lost opportunity costs...more