Latest Publications

Share:

Loss of profit recoverable in terminated DBO procurement

Can a breach of one contract give rise to liability for lost profit on a related contract? Or is the loss too "remote"? A Privy Council decision from Monday of this week addressed this issue in the context of a design, build,...more

Offshore wind projects: delays during construction

The offshore wind sector continues to grow at an unprecedented rate, particularly in Europe, and increasingly in Asia and North America. The construction phase of any project is vulnerable to delay. That is particularly the...more

Liquidated damages and penalties in Singapore

Liquidated damages provisions in contracts are unenforceable if they constitute a "penalty". The past few years have seen subtle but important shifts in how the concept of a penalty is defined. A recent decision from the...more

PFI: benchmarking and market testing, a cause of conflict in the long run?

The ongoing Scottish case of Serco Limited v Forth Health Limited highlights the difficulties that can arise when applying benchmarking and market testing provisions in long-term maintenance and service...more

Claims Against Subcontractors: Contingent Loss, No Recovery?

A main contractor is often in a difficult position during project disputes, caught in the middle between its liabilities to the employer and its ability to recover those losses from its subcontractors. But, what happens when...more

Construction contracts: ambiguities in remeasurement provisions

Remeasurement provisions are commonly used in construction and engineering contracts where there is uncertainty as to the quantity of work to be performed by the contractor. Remeasurement may be desirable in these situations,...more

Shifting foundations: amendments to ground conditions clauses

Amending standard forms of construction and engineering contracts to change the risk level between the parties is a perennial issue. This, however, can lead to disputes due to amendments not clearly reflecting the intention...more

Construction contracts: vesting of title to goods

When does title to goods transfer from a contractor to an employer? This can be a critical issue, especially when a party to a project has become insolvent. A recent English case considered this issue, and the application of...more

Subcontracting without consent – when performance gets personal

Restrictions on a contractor's rights to subcontract works are common across industry forms of contract, and breach of these provisions can have significant consequences for a contractor. In a recent Australian case, the...more

Disputes between members of a construction joint venture

The case of Doosan Enpure Limited v Interserve Construction Limited represents a rare consideration by the English High Court of a dispute between members of a construction joint venture. The court found that Interserve was...more

Turning off auto-correct? Employers' ability to recover costs of correcting contractors' defects

In Thio Keng Thay v Sandy Island Pte Ltd [2019] SGHC 175 the High Court of Singapore confirmed that an employer may recover damages for rectifying defects even when it has done so in breach of a contractual defects...more

Construction contracts: "No damage for delay" clause enforced

In a recent case, the Federal Court of Australia confirmed that it will enforce a "no damage for delay" clause, including when delay occurs as a result of a variation under a contract....more

Security of payment: claiming a sum that “may” be due?

A recent decision by Singapore's highest court has held that a contractor must first establish that it is entitled to payment under the contract in order to claim progress payments under the Security of Payment Act, raising...more

When Do Defects Prevent Practical Completion?

Practical completion represents the physical completion of works on construction projects. Despite its importance, it is not a legal term of art, and whether or not practical completion has been achieved requires...more

Striking out total cost claims

A "global" or "total cost" claim is one in which the damages calculation is derived from the total cost of the work incurred by a contractor, minus the bid amount. Such claims are increasingly used by contractors where...more

The New Enforcement Regime: a further step in the right direction

The United Arab Emirates has introduced further reforms regulating the enforcement of foreign arbitral awards. In the last year, the UAE has taken a significant step towards aligning the UAE's arbitration laws with...more

Liquidated damages in energy projects

In a noteworthy decision to participants in the energy industry, the High Court of England & Wales examined what constitutes a valid liquidated damages clause in the event of delayed completion of a solar project. And last...more

42 Results
 / 
View per page
Page: of 2

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide