On March 12, 2024, the U.S. Court of Appeals for the Third Circuit upheld a prospective rule change to PJM Interconnection, L.L.C.’s (“PJM”) annual capacity auction but struck down attempts by PJM and FERC to apply the rule...more
On March 21, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 2023-A (Final Rule), which reaffirmed aspects of Order No. 2023 — the Commission’s landmark order updating its generator...more
On December 19, 2023, the Department of Energy (“DOE”) Grid Deployment Office released final guidance on how it will designate National Interest Electric Transmission Corridors (“NIETC”) pursuant to Section 216(a) of the...more
On December 20, 2023, FERC approved the California Independent System Operator Corporation’s (“CAISO”) proposal to establish the Extended Day Ahead Market (“EDAM”), which allows external Balancing Authority Areas (“BAAs”) to...more
On November 17, 2023, the U.S. Court of Appeals of the District of Columbia Circuit (“D.C. Circuit”) denied petitions challenging FERC’s approval of recent changes to the PJM Interconnection, L.L.C.’s (“PJM”) Open Access...more
On November 16, 2023, FERC staff issued the 2023-2024 Winter Energy Market and Electric Reliability Assessment report, projecting trends and identifying considerations for energy markets and electric reliability for the...more
On October 20, 2023, the U.S. Department of Energy (“DOE”) released the National Transmission Needs Study, a triennial report that assesses electric transmission capacity constraints and congestion on a national scale. While...more
On October 19, 2023, FERC issued a final rule directing the North American Reliability Corporation (“NERC”) to develop or modify reliability standards to address reliability concerns attributable to inverter-based resources...more
11/9/2023
/ Bulk Electric System ,
Energy Sector ,
FERC ,
Final Rules ,
Infrastructure ,
NERC ,
Photovoltaic ,
Reliability Standards ,
Renewable Energy ,
Solar Energy ,
Transmission Grid ,
Utilities Sector ,
Wind Power
On August 10, 2023 in response to incentives made available through the Bipartisan Infrastructure Law and the Inflation Reduction Act, the U.S. Department of Energy (“DOE”) proposed reforms to its regulations governing the...more
On July 28, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 2023 (Order No. 2023 or Final Rule), which updates the procedures for interconnecting large generating facilities (20MW and above)...more
8/4/2023
/ Electric Generation Suppliers ,
Energy Market ,
Energy Policy ,
Energy Projects ,
Energy Reform ,
Energy Sector ,
Energy Storage ,
FERC ,
Final Rules ,
Infrastructure ,
Interconnections ,
ISO/RTO ,
Notice of Proposed Rulemaking (NOPR) ,
Renewable Energy ,
SGIP
On July 7, 2023, the U.S. Court of Appeals for the District of Columbia Circuit (“D.C. Circuit”) issued an opinion rejecting petitioner Hecate Energy Green County 3 LLC’s (“Hecate”) claim that the New York Independent System...more
Introduction -
On June 29, the Federal Energy Regulatory Commission (FERC or Commission) issued Order No. 898, a final rule that revises FERC’s Uniform System of Accounts (USofA) by adding functional detail concerning the...more
In its May 26, 2023 opinion in Sierra Club v. Federal Energy Regulatory Commission, the United States Court of Appeals for the District of Columbia Circuit addressed challenges to its jurisdiction to hear appeals of...more
On May 26, 2023, the United States Court of Appeals for the District of Columbia Circuit issued an opinion in Sierra Club v. Federal Energy Regulatory Commission largely denying challenges to several FERC orders authorizing...more
On May 3, 2023, a divided FERC voted 3-1 to deny a widely-supported complaint by multiple utilities in the Southwest Power Pool (“SPP”) region arguing that the absence of the new 15% generation Planning Reserve Margin...more
On March 16, 2023, FERC granted a petition declaring that, should it issue orders pursuant to Sections 210 and 211 of the Federal Power Act (“FPA”), which would be required for a prospective project to interconnect Puerto...more
On February 10, 2023, FERC approved the Western Resource Adequacy Program (“WRAP”) proposed by the Western Power Pool (“WPP”). The voluntary program commits participants to demonstrate prior to a given Winter or Summer season...more
On January 19, 2023, FERC established that a facility’s classification as transmission or distribution under criteria established in the Southwest Power Pool, Inc.’s (“SPP”) Open Access Transmission Tariff (“Tariff”) can be...more
On December 16, 2022, FERC again rejected the Midcontinent Independent System Operator Inc. (“MISO”) proposal for Transmission Owners to self-fund Necessary Upgrades to connect Merchant High Voltage Direct Current (“HVDC”)...more
On November 18, 2022, FERC accepted a September 19, 2022 proposal from the California Independent System Operator (“CAISO”) to correct “excessively high” payments being made to electric storage resources that are forced to...more
On November 17, 2022, FERC approved an application authorizing Commonwealth LNG, LLC (“Commonwealth”) to site, construct, and operate a liquified natural gas (“LNG”) export terminal in Cameron Parish, Louisiana. The LNG...more
On November 2, 2022, FERC denied a complaint brought by the Iowa Coalition for Affordable Transmission (“ICAT”) alleging that ITC Midwest, LLC’s (“ITC Midwest”) capital structure, with a targeted 60%-40% equity-to-debt ratio,...more
On August 31, 2022, FERC issued two orders regarding two proposals to revise the Midcontinent Independent System Operator’s (“MISO”) resource adequacy requirements. In the first order, FERC accepted MISO’s proposal to move to...more
On July 28, 2022, FERC proposed changes to its Uniform System of Accounts (“USofA”) in response to the growth of non-hydro renewable generation such as wind, solar, and storage and codify accounting for renewable energy...more