On April 17, the California Court of Appeal decided Crosno Construction, Inc. v. Travelers Casualty & Surety Company of America, effectively narrowing the scope of enforceable “pay-when-paid” provisions in construction...more
On April 17, the California Court of Appeal decided Crosno Construction, Inc. v. Travelers Casualty & Surety Company of America, effectively narrowing the scope of enforceable “pay-when-paid” provisions in construction...more
Construction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays...more
12/12/2019
/ Acceleration ,
Claim Procedures ,
Construction Contracts ,
Construction Disputes ,
Construction Litigation ,
Construction Project ,
Contract Disputes ,
Contract Terms ,
Contractors ,
Cost Recovery ,
Damages ,
Delay Claims ,
Development Approval Extensions ,
No Damage For Delay ,
Real Estate Development ,
Real Estate Market