Latest Publications

Share:

Court of Federal Claims Provides Guidance on Implied-in-Fact Contracts

In Panther Brands, LLC v. The United States, No. 16-1157C (December 17, 2019), the Court of Federal Claims addressed the elements of an implied-in-fact contract in the context of a motion for summary judgment dismissal of the...more

Civilian Board of Contract Appeals Decision Highlights Importance of Consistent Project Records

In AMEC Foster Wheeler Environmental & Infrastructure, Inc., CBCA 5168, 6298 (November 13, 2019), the Civilian Board of Contract Appeals rejected in large part a federal contractor’s claims due to inconsistencies between the...more

Court of Federal Claims Provides Guidance on Recovery of Unabsorbed Overhead and the Christian Doctrine

In Kudsk Construction Inc. v. The United States, No. 18-1032C (August 30, 2019), the Court of Federal Claims addressed damages in the context of a delayed notice to proceed and addressed the Christian doctrine in the context...more

ASBCA Provides Guidance on CENTCOM Default Termination Decision

In Watts Constructors, LLC, (June 24, 2019), the Armed Services Board of Contract Appeals (ASBCA) provided further guidance on its earlier decision ECC CENTCOM, 18-1 BCA 37,133. ...more

The Court of Federal Claims Provides Guidance on Factors for the Government to Consider in a Default Termination

A recent case from the Court of Federal Claims provides us instruction on the factors that the government should consider in determining whether to terminate a construction contract for default. This case provides a detailed...more

The Court of Federal Claims Provides Guidance on Differing Site Conditions and Superior Knowledge Claims

A recent case from the Court of Federal Claims provides us instruction on differing site conditions and superior knowledge claims. The case arose out of a maintenance dredging contract issued by the United States Army Corps...more

Buyer Beware—The Risks of Settling a Subcontractor Claim

A recent case from the Armed Services Board of Contract Appeals provides us with a reminder of what can happen to a prime contractor when it settles a subcontractor claim and then seeks to pass through the settlement amount...more

The Court of Federal Claims Provides Guidance on Cardinal and Constructive Change Law

A recent case from the Court of Federal Claims provides us with a useful summary of several legal principles applicable to constructive changes and cardinal changes. The case arose out of a contract to supply mail processing...more

The ASBCA Imposes Conditions on Raising Excusable Delay as an Affirmative Defense to Default Termination

A recent decision by the Armed Services Board of Contract Appeals underscores the importance of timely filing a certified claim for excusable delay, and the risks of failing to do so. In ECC CENTCOM Constructors, Inc....more

Lock ‘Em Up or Lose ‘Em — The Importance of Early Execution of Key Subcontracts

A recent decision by the Armed Services Board of Contract Appeals reminds us of the importance of obtaining commitments from your key subcontractors after award....more

The Importance of Modifications and Schedule Updates When Faced with a Termination for Default

A recent decision by the Armed Services Board of Contract Appeals reminds us of the significance of release language in a modification, this time in the context of a contractor seeking to overturn a termination for default of...more

Overturning a Termination for Cause

A recent decision by the Armed Services Board of Contract Appeals provides guidance on overturning a termination for cause of a supply contract. In AEY, Inc. (June 22, 2018), the ASBCA in large part overturned the...more

Time is Money—Recent Decisions on Liquidated Damages (Part II)

The second significant recent ASBCA decision on liquidated damages is American International Contractors, Inc. (May 29, 2018). In that case, the contractor did not complete the original contract work on time and was assessed...more

Time is Money—Recent Decisions on Liquidated Damages

A recent decision by the Armed Services Board of Contract Appeals reminds us how important it is to remember to ask for time as well as money when pursuing claims against the government....more

Government Contractor May Proceed With Delay Claim Notwithstanding Incomplete Project

A recent decision by the Civilian Board of Contract Appeals rejected the Government’s attempt to stay an appeal seeking recovery for delay damages “until the project is complete.” In CTA I, LLC v. Department of Veterans...more

Collateral Estoppel—What is Good for the Goose May Not Be Good For the Gander

A recent decision by the Civilian Board of Contract Appeals reminds us that all findings of fact made by a court are not created equal, at least insofar as they are applied in a subsequent proceeding. In VSE Corporation v...more

Government Contractor Awarded Equitable Adjustment for Negligent Quantities Estimate in Fixed Price Contract

A recent decision by the United States Court of Federal Claims reminds us how important the Government’s estimated quantities are, even in a fixed price contract. In Agility Defense & Government Services, Inc. v United States...more

Stiff Penalties Imposed for Abuse of SBA Set Aside Contracts

This past Tuesday, Margaret Cho, an Officer of Far East Construction Company, pleaded guilty to conspiring to commit wire fraud. Ms. Cho also agreed to pay a forfeiture in the amount of $169,166 and a criminal fine in the...more

State of Alaska Tightens Its Claim Provisions

In 2015, the Alaska Department of Transportation and Public Facilities significantly amended the claims provision of its Standard Specifications—105-1.17. The amendments incorporate language from the standard conditions...more

44 Results
 / 
View per page
Page: of 2

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide