Summary
The government has published the draft Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations. In this Insight, Katharine Tulloch and Corinna Whittle take a closer look at them.
On 20 December 2022, the government published the draft Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations (Regulations) together with the Government response to the Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations (Response).
The plan is for the Regulations to come into force on 6 April 2023. The Regulations apply to England.
This Insight takes a closer look at the Regulations and Response.
Recap
Higher-risk buildings are those buildings that will be required to meet the legal requirements of the more stringent regime for building safety introduced by the Building Safety Act 2022 (BSA).
There are two parts to the new regime:
- the design and construction of new higher-risk buildings and building works to existing higher-risk buildings; and
- the occupation of higher-risk buildings.
The Regulations together with the BSA:
- define which buildings are considered “higher-risk buildings” for design and construction under s120D of the Building Act 1984 (inserted by s31 BSA);
- define which buildings are excluded from higher-risk buildings for occupation under s65 BSA;
- provide an overall definition for building for both parts of the regime under s120D Building Act and s65 BSA;
- establish how height and the number of storeys a building has is determined for higher-risk buildings.
Design and construction regime – which buildings?
Buildings subject to this regime include those which:
- are at least 18 metres in height or at least 7 storeys;
- contain at least two residential units. The Response clarifies that “residential unit” means “a dwelling or any other unit of living accommodation, for example a flat or rooms in a university hall of residence where amenities are shared…”.
Care homes and hospitals which are 18 metres in height or at least 7 storeys will also be subject to the new regime.
Buildings excluded from the regime include:
- a building that comprises entirely of:
- a secure residential institution;
- a hotel;
- military barracks;
- a building that contains living accommodation provided by the Ministry of Defence (either alone or in combination with other accommodation);
- a building that contains living accommodation (either alone or in combination with other accommodation) for:
- His Majesty’s forces;
- any visiting force or an international headquarters or defence organisation designated for the purposes of the International Headquarters and Defence Organisations Act 1964(1).
The government’s rationale for excluding hospitals and care homes is because they are already regulated as workplaces by the Regulatory Reform (Fire safety) Order 2005 (Order) and subject to the local Fire and Rescue Authorities’ and the Care Quality Commission’s inspection regimes. Likewise, the exclusion of hotels and secure residential institutions is because these buildings in occupation are already regulated by the Order and have additional safety measures in place such as being staffed 24/7 and having a higher level of alarm and detection facilities. This explains the wider exclusions for occupied buildings, as opposed to those in the construction phase.
What's next?
The Regulations have been laid before Parliament and are subject to the affirmative parliamentary procedure. This means they will be debated by both Houses of Parliament and so may be subject to change. If approved, they will come into force on 6 April 2023.
The government has said that it will publish full guidance once the Regulations are approved by Parliament. According to the Response, “This will be made available before the first parts of the new regime come into force and become legal requirements.”