FCC Refuses to Grant Leniency on Construction of New Radio Station After Construction Permit Deadline - Cancels Permit

Davis Wright Tremaine LLP
Contact

When building a new radio station, the FCC gives broadcasters three years in which to construct.  The deadline for construction can only be extended for limited reasons (referred to as circumstances that justify "tolling" of the permit) - for a short term equal to the period that an Act of God (e.g. a hurricane, blizzard or flood that restricts access to the proposed transmitter site) delays construction, for a Court appeal of an adverse zoning ruling, or for an appeal or challenge to the underlying grant of the construction permit itself.  While waivers of these deadlines are possible - they are very rare, and usually granted only where the completion of construction misses the deadline by a matter of days.  In a case decided last week, the FCC reiterated its policy, and canceled a construction permit for a new AM station despite the fact that the station towers had allegedly been constructed, as it appeared that even that construction occurred after the construction deadline, and there was no clear time frame in which the final steps would be taken (including the proof of performance) that would allow the station to file a license application showing that all construction had been completed in accordance with the parameters set out in the construction permit.

Please see full article below for more information.

Please see full publication below for more information.

LOADING PDF: If there are any problems, click here to download the file.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Davis Wright Tremaine LLP | Attorney Advertising

Written by:

Davis Wright Tremaine LLP
Contact
more
less

PUBLISH YOUR CONTENT ON JD SUPRA NOW

  • Increased visibility
  • Actionable analytics
  • Ongoing guidance

Davis Wright Tremaine LLP on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide