Joint Check Agreement Causes Big Trouble in Virginia

Woods Rogers
Contact

Many general contractors manage the risk of a subcontractor’s financial instability by issuing joint checks to the subcontractor and its suppliers on a project. These arrangements are usually governed by a separate agreement that sets forth the roles and rights of the parties, and limits the general contractor’s liability to sub-subcontractors and suppliers with whom the general contractor does not have a contract. A recent decision by the Virginia Supreme Court now calls into question this common practice. As a result, contractors need to review and modify their joint check agreements and procedures regarding communications with lower tier entities to limit the risk of effectively paying twice.

In the case of James G. Davis Construction Corp. v. FTJ, Inc., 2020 Va. LEXIS 42 (Va., May 14, 2020), Davis was a general contractor for a condominium project and subcontracted the drywall work to H&2 Drywall Contractors. H&2 purchased its drywall materials from FTJ, Inc. and entered into a joint check agreement with H&2 and Davis that contained terms similar to many joint check agreements that contractors use, including:

      • That any checks for materials would be made payable jointly to H&2 and FTJ;
      • That Davis will only make payments to the extent Davis actually owes money to H&2 on the project;
      • That the sole purpose of the agreement was to assist H&2 in making payment to FTJ; and
      • That nothing in the agreement creates any contractual relationship or equitable obligation between FTJ and Davis.

Predictably, H&2 ran into financial difficulties and was unable to complete its work on the project. Davis informed FTJ to stop shipping materials and then terminated H&2. Davis advised FTJ that its past due invoices were being processed, but Davis later refused to pay FTJ once Davis determined it had incurred costs beyond the remaining subcontract value to complete H&2’s scope of work. Davis relied on the language in its joint check agreement that it was not liable to FTJ because it did not owe H&2 anything further on the project.

The Virginia Supreme Court affirmed the trial court’s determination that Davis was liable to FTJ not by contract, but by the equitable theory of unjust enrichment. Even though the costs of completing the subcontract work exceeded its value, the court found that Davis had not paid for all of the drywall and was unjustly enriched by using it for the project. Prior to this case, courts in Virginia were not receptive to such claims and generally, the only relief available was through the express agreement between the parties (breach of contract), or enforcement of a validly filed mechanic’s lien or payment bond claim. This upsets the common assumption that a party is only liable for economic loss to those with whom it contracts.

Contractors commonly seek continued performance from suppliers when a subcontractor faces trouble to keep a project on track. This has now become a more complicated and risky process. 

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations. Attorney Advertising.

© Woods Rogers

Written by:

Woods Rogers
Contact
more
less

PUBLISH YOUR CONTENT ON JD SUPRA NOW

  • Increased visibility
  • Actionable analytics
  • Ongoing guidance

Woods Rogers on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide