Pa. DEP Sets Early 2018 for Final Methane General Permits for Oil and Gas Drillers

Saul Ewing LLP
Contact

Saul Ewing Arnstein & Lehr LLP

Summary

​As part of Governor Wolf’s strategy to reduce methane emissions from oil and gas sites, the Pennsylvania Department of Environmental Protection published draft final permit revisions for the new GP-5A, GP-5 and Exemption 38. When issued, the revised Exemption 38 will specify criteria for exempting existing and new or modified oil and gas exploration, development and production facilities from Plan Approval requirements, and revised GP-5 and new GP-5A will be available for facilities that are not exempt from the requirement for having a Plan Approval prior to construction. The new GP-5A permit will apply to unconventional gas wells and remote pigging stations, while the revised GP-5 will apply to natural gas compression stations, processing plants, and transmission stations.

Both GPs incorporate the most current state and federal regulatory requirements for facilities constructed or modified after the effective date.

The proposed General Permits were first published in February of 2017. The public comment period closed in June with more than 10,500 comments from advisory boards, committees, industry and environmental groups. Copies of the proposed GPs and Exemption 38 are available here. The draft permits are set to go before the Air Quality Technical Advisory Committee on December 14, 2017. Final approval of Exemption 38 and the GPs is not expected until first quarter of 2018.

Some of the changes include:

  • Reduction in the number of pages by directly referencing federal regulations for sources that do not differ from state Best Available Technology (BAT) determinations.
  • BAT determinations for certain sources were revised based on comments received.
  • Provisions for temporary sources were removed from GP-5A and placed under the revised Exemption 38.
  • Clarification of various terms and conditions in the proposed General Permits.
  • A transition period was added to manage the implementation of the General Permits.

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Saul Ewing LLP | Attorney Advertising

Written by:

Saul Ewing LLP
Contact
more
less

PUBLISH YOUR CONTENT ON JD SUPRA NOW

  • Increased visibility
  • Actionable analytics
  • Ongoing guidance

Saul Ewing LLP on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide