United States Solar – The Shift from Utility Scale to Distributed Generation

Akin Gump Strauss Hauer & Feld LLP
Contact

In the first half of this decade, solar developers in the United States were largely focused on utility scale projects. “Mega-projects,” such as SunPower’s approximately 580 MW Solar Star projects, First Solar’s 550 MW Topaz project and BrightSource’s 377 MW Ivanapah project, exemplify the industry’s success.     

Yet, even with more than 18GW of utility scale solar expected to be online in the United States by 2016, the future growth of the U.S. solar market will likely be through distributed generation projects (panels on homes, businesses, car parks, etc.) instead of large-scale utility projects. Fewer power purchase agreements, stringent regulatory requirements and the impending decrease in the ITC have made utility scale projects more difficult to develop and finance, causing developers to shift their focus to distributed generation projects. 

In recent years, fewer power purchase agreements (PPAs) have become available for potential projects. In some states, utilities are issuing fewer requests for proposals for large scale PPAs as they come closer to achieving their state-mandated renewable portfolio standards with current PPAs. For example, the three major California utilities (San Diego Gas & Electric, Pacific Gas & Electric and Southern California Edison) have a surplus of MWs contracted under PPAs that will allow them to meet their 33 percent RPS requirement even if all of the projects do not move forward. In other states, the lack of enforcement mechanisms for renewable portfolio mandates have not required the utilities to make power purchase agreements available for renewable projects. 

In addition, the significant drop in PPA prices for renewable energy projects in the past five years1 makes large-scale solar projects less attractive to investors and more difficult to finance. Utilities have even reopened the PPA price in certain cases as projects move from the development stage to the construction stage. The uncertainty caused by the lack of supply of PPAs and lower PPA prices have made large scale projects more difficult to finance. Distributed generation projects have a guaranteed offtaker and, due to their lower costs, are easier to finance or do not require financing at all.

Reduced equipment and installation costs are another impetus for the shift of the market to distributed generation. The cost of utility scale solar decreased by 15 percent in 2013 from $2.27/W in Q4 2012 to $1.96/W in Q4 2013.2  As the cost of equipment declines, the economies of scale once gained from large-scale solar projects are dampened by the cost of acquiring land and navigating difficult regulatory regimes. Distributed generation projects are not subject to environmental, permitting or biological testing requirements.

Finally, the reduction of the ITC from 30 percent to 10 percent at the beginning of 2017 is another driving force. The ITC has been an important piece of financing for utility scale projects. The decrease will create a gap in financing for projects that are not online by the end of 2016. In sum, any utility scale project not currently under development will only be able to qualify for the reduced ITC rate.

The distributed generation market is not without challenges. A number of states (including Arizona, Colorado and California) are considering changes to their net metering policies that could adversely impact the benefit of distributed generation systems to homeowners and businesses. However, the distributed generation market is not anticipated to be significantly harmed by these changes since the decreasing cost of solar system installation is expected to offset these impacts.


1 For example, in the western United States, PPA prices for PV solar projects were approximately $150/MW in 2008 and recently were approximately $60/MW. 

2 U.S. Solar Market Insight Report: 2013 Year-in-Review, GTM Research and Solar Energy Industries Association.

 

DISCLAIMER: Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.

© Akin Gump Strauss Hauer & Feld LLP | Attorney Advertising

Written by:

Akin Gump Strauss Hauer & Feld LLP
Contact
more
less

PUBLISH YOUR CONTENT ON JD SUPRA NOW

  • Increased visibility
  • Actionable analytics
  • Ongoing guidance

Akin Gump Strauss Hauer & Feld LLP on:

Reporters on Deadline

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
Custom Email Digest
- hide
- hide