Residential Contractor Boot Camp
Construction and the Neighbors
California Court of Appeal Opens Doors for Construction Defect Claims Outside of the Right to Repair Act
In NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), 2024 WL 1270188 (2d Cir. Mar. 26, 2024), the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s grant of summary judgment dismissing a...more
On Monday, June 17, 2024, the Supreme Judicial Court (“SJC”) issued its decision in Business Interiors Floor Covering Business Trust v. Graycor Construction Company, Inc., et al, which interprets the Massachusetts Prompt...more
The High Court has provided guidance on a contractor’s general right to suspend works, the enforceability of liquidated damages upon termination, and the recoverability of financing costs as part of loss of revenue....more
The Canadian Institute’s 15th Annual Conference on Managing Risk in Construction Contracts & Projects, Western Canada Edition is returning to Edmonton on January 25-26, 2023. This two-day conference is specifically...more
My commute home last night took longer than usual. It was not excessive traffic, an accident, or a stalled car. Rather, the cause of my delayed commute was a turtle: one single turtle crossing the road, holding up about 30...more
The winter storm that brought snow, freezing temperatures, power outages, frozen water lines and bursting pipes to Texas, shutting down most construction projects in the process, forced many contractors and owners to take a...more
In WDF, Inc. v. City of New York, No. 652478 (N.Y. Sup.) (Mar. 12, 2021), the contractor filed suit to recover damages from the City on numerous combined waste water treatment projects. The contractor claimed that the City...more
In a recent decision likely to have a significant impact upon the way private construction projects in Massachusetts are managed, the Superior Court recently construed the Massachusetts Prompt Pay Statute in the way the...more
It happens all the time! The owner-contractor agreement contains a “no damages for delay” clause; a clause requiring that all changes be in writing before work is performed; and a clause requiring partial lien waivers and...more
Technology is constantly evolving the construction and engineering industries. Recent trends include: - Big Data – using historical big data to improve efficiency - Artificial Intelligence (AI) – leveraging automation to...more
Join Miles mediator and arbitrators Jennifer Grippa and David Matthews, along with Frank Brown, partner in Weissman Law and General Counsel of the Greater Atlanta Home Builders Association, Inc., Jerry Warshaw, Founder and...more
D.A. Nolt, Inc. v. The Philadelphia Municipal Authority, 2020 BL 199761 (E.D. Pa. May 28, 2020) - The Philadelphia Municipal Authority (the “Authority”) contracted D.A. Nolt, Inc. (“Nolt”) to renovate a building that would...more
Construction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays...more
It almost goes without saying that if you have to pursue or defend a delay claim, you are going to need some evidence (preferably by an expert) to establish or to challenge entitlement to the damages sought. And we all know...more
I just blogged about asking for what you want and the importance of complying with notice provisions in pursuing a construction claim. A court in Oklahoma just reminded me that not all claims require notice. Here’s what I...more
Given the amount of leftover Halloween candy in our house, you bet that I can make some deals with my kiddos: “If you do this, I will give you some candy” … or … “If you don’t stop doing this … I won’t give you any candy.”...more
United States ex rel. Am. Civ. Constr., LLC v. Hirani Eng’g & Land Surveying, P.C., 2018 U.S. Dist. LEXIS 200829 (D.D.C. Nov 28, 2018). The case involved the construction of a levee wall on the National Mall in Washington,...more
Fisk Elec. Co. v. DQSI, L.L.C., 2018 U.S. App. LEXIS 17914 (5th Cir., June 29, 2018) - DQSI, L.L.C., (“DQSI”) a general contractor, was hired by the Army Corps of Engineers (“Corps”) for a pump station construction...more
Woodrow Wilson Constr. LLC v. Orleans Par. Sch. Bd., 2018 La. App. LEXIS 762 (April 18, 2018) - The Orleans Parish School Board (“OPSB”) awarded a prime contract to Woodrow Wilson Construction (“WWC”) for the construction...more
Sovereign immunity is the legal doctrine, dating back to the days of the British monarchy, that a sovereign or state cannot commit a legal wrong and is immune from suit: in essence, “the king can do no wrong.” ...more
On a high level, construction delay litigation involves sorting out the impacts to the critical project path and determining which party is responsible for those impacts. One of the more difficult elements of this process is...more
D.W. Wilburn, Inc. v. K. Norman Berry Assocs., No. 2015-CA-001254-MR, 2016 Ky. App. Lexis 206 (Ky. Ct. App. Dec. 22, 2016) - This case arose out of a construction project in which the Oldham County Board of Education...more