Construction Disputes Delay Claims Contract Terms

Robinson+Cole Construction Law Zone

Second Circuit Affirms Win for General Contractor on No Damages for Delay Provision

In NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), 2024 WL 1270188 (2d Cir. Mar. 26, 2024), the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s grant of summary judgment dismissing a...more

Goulston & Storrs PC

Owners Beware: Massachusetts Supreme Judicial Court Underscores Strict Adherence to Prompt Payment Act

Goulston & Storrs PC on

On Monday, June 17, 2024, the Supreme Judicial Court (“SJC”) issued its decision in Business Interiors Floor Covering Business Trust v. Graycor Construction Company, Inc., et al, which interprets the Massachusetts Prompt...more

A&O Shearman

Watts at stake when there's a delay?

A&O Shearman on

The High Court has provided guidance on a contractor’s general right to suspend works, the enforceability of liquidated damages upon termination, and the recoverability of financing costs as part of loss of revenue....more

Gray Reed

Excusable Delay and Builder’s Risk: A Reminder to Weatherproof Your Contracts

Gray Reed on

The winter storm that brought snow, freezing temperatures, power outages, frozen water lines and bursting pipes to Texas, shutting down most construction projects in the process, forced many contractors and owners to take a...more

Burr & Forman

Pre-Bid Documents and Estimates Can’t Be Hidden Behind the Curtain in Disputed Delay Claims

Burr & Forman on

In WDF, Inc. v. City of New York,  No. 652478 (N.Y. Sup.) (Mar. 12, 2021), the contractor filed suit to recover damages from the City on numerous combined waste water treatment projects.  The contractor claimed that the City...more

Robinson+Cole Construction Law Zone

The Massachusetts Prompt Pay Statute: A Cautionary Tale for Those Who Don’t Read the Fine Print

In a recent decision likely to have a significant impact upon the way private construction projects in Massachusetts are managed, the Superior Court recently construed the Massachusetts Prompt Pay Statute in the way the...more

Burr & Forman

Court Recognizes Day-to-Day Changes Are Compensable Despite Contractual Waivers

Burr & Forman on

It happens all the time! The owner-contractor agreement contains a “no damages for delay” clause; a clause requiring that all changes be in writing before work is performed; and a clause requiring partial lien waivers and...more

Troutman Pepper

Federal Court in PA Finds Liquidated Damages Provision Unenforceable Where the Per Day Liquidated Damage Amount Was Copied from...

Troutman Pepper on

D.A. Nolt, Inc. v. The Philadelphia Municipal Authority, 2020 BL 199761 (E.D. Pa. May 28, 2020) - The Philadelphia Municipal Authority (the “Authority”) contracted D.A. Nolt, Inc. (“Nolt”) to renovate a building that would...more

Troutman Pepper

Does a No-Damage-for-Delay Clause Also Preclude Acceleration Damages?

Troutman Pepper on

Construction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays...more

Burr & Forman

9 Best Practice Tips for a Schedule Analysis of Construction Delays

Burr & Forman on

It almost goes without saying that if you have to pursue or defend a delay claim, you are going to need some evidence (preferably by an expert) to establish or to challenge entitlement to the damages sought. And we all know...more

Burr & Forman

Payment of Retainage with “conditions attached” Deemed Non-Payment

Burr & Forman on

Given the amount of leftover Halloween candy in our house, you bet that I can make some deals with my kiddos: “If you do this, I will give you some candy” … or … “If you don’t stop doing this … I won’t give you any candy.”...more

White & Case LLP

Liquidated Damages for Post-Termination Delay?

White & Case LLP on

The High Court of England & Wales considered, in respect of the delayed completion of a solar project, the appropriate end date for liquidated damages under a terminated construction contract....more

12 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide