Delay Claims Construction Project Construction Litigation

Robinson+Cole Construction Law Zone

Second Circuit Affirms Win for General Contractor on No Damages for Delay Provision

In NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), 2024 WL 1270188 (2d Cir. Mar. 26, 2024), the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s grant of summary judgment dismissing a...more

American Conference Institute (ACI)

[Event] Managing Risk in Construction Contracts & Projects – Western Canada Edition - January 25th - 26th, Edmonton, Canada

The Canadian Institute’s 15th Annual Conference on Managing Risk in Construction Contracts & Projects, Western Canada Edition is returning to Edmonton on January 25-26, 2023. This two-day conference is specifically...more

Stoel Rives -  Ahead of Schedule

Who Owns the Project’s ‘Float,’ and What Should Be Done About It?

The coined phrase “time is money” especially applies in the construction industry. Construction participants go to great lengths to build their projects on time and avoid delay costs. To facilitate timely project completion,...more

Buchalter

Pre-Bid Documents and Estimates Can’t Be Hidden Behind the Curtain in Disputed Delay Claims

Buchalter on

In WDF, Inc. v. City of New York,  No. 652478 (N.Y. Sup.) (Mar. 12, 2021), the contractor filed suit to recover damages from the City on numerous combined waste water treatment projects.  The contractor claimed that the City...more

Buchalter

Court Recognizes Day-to-Day Changes Are Compensable Despite Contractual Waivers

Buchalter on

It happens all the time! The owner-contractor agreement contains a “no damages for delay” clause; a clause requiring that all changes be in writing before work is performed; and a clause requiring partial lien waivers and...more

Buchalter

No Longer in the Dark: A Primer on the Distinction between Delay and Disruption Damages in a Construction Dispute

Buchalter on

If you are left in the dark about something, you don’t have the information you should have to make an informed decision. Delay claims on a construction can be confusing, especially when you think about the delay to the work...more

TransPerfect Legal

Using Legal Technology to Navigate Complex Data in Construction Arbitration

TransPerfect Legal on

Technology is constantly evolving the construction and engineering industries. Recent trends include:   - Big Data – using historical big data to improve efficiency - Artificial Intelligence (AI) – leveraging automation to...more

Miles Mediation & Arbitration

[Webinar] Construction ADR Webinar: Residential & Multi-Family Construction Disputes: Is There A Practical Solution? - September...

Join Miles mediator and arbitrators Jennifer Grippa and David Matthews, along with Frank Brown, partner in Weissman Law and General Counsel of the Greater Atlanta Home Builders Association, Inc., Jerry Warshaw, Founder and...more

Troutman Pepper

Federal Court in PA Finds Liquidated Damages Provision Unenforceable Where the Per Day Liquidated Damage Amount Was Copied from...

Troutman Pepper on

D.A. Nolt, Inc. v. The Philadelphia Municipal Authority, 2020 BL 199761 (E.D. Pa. May 28, 2020) - The Philadelphia Municipal Authority (the “Authority”) contracted D.A. Nolt, Inc. (“Nolt”) to renovate a building that would...more

Troutman Pepper

Does a No-Damage-for-Delay Clause Also Preclude Acceleration Damages?

Troutman Pepper on

Construction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays...more

Buchalter

9 Best Practice Tips for a Schedule Analysis of Construction Delays

Buchalter on

It almost goes without saying that if you have to pursue or defend a delay claim, you are going to need some evidence (preferably by an expert) to establish or to challenge entitlement to the damages sought. And we all know...more

Buchalter

When Does A Claim for Damages Not Require Notice? When It Is One For Liquidated Damages.

Buchalter on

I just blogged about asking for what you want and the importance of complying with notice provisions in pursuing a construction claim.  A court in Oklahoma just reminded me that not all claims require notice.  Here’s what I...more

Troutman Pepper

Federal Court Clarifies When Idle Equipment Costs Are Recoverable Under the Miller Act

Troutman Pepper on

United States ex rel. Am. Civ. Constr., LLC v. Hirani Eng’g & Land Surveying, P.C., 2018 U.S. Dist. LEXIS 200829 (D.D.C. Nov 28, 2018). The case involved the construction of a levee wall on the National Mall in Washington,...more

Troutman Pepper

Concurrent Delay: Surety—Standing in the Shoes of Subcontractor—Is Barred From Asserting Defense of Concurrent Delay Because...

Troutman Pepper on

Fid. & Deposit Co. of Md. v. Travelers Cas. & Sur. Co. of Am., 2018 U.S. Dist. LEXIS 162265 (D. Nev., September 21, 2018) - Clark County School District (“CCSD”) hired Big Town Mechanical (“Big Town”) as general contractor...more

Troutman Pepper

Federal Court in Pennsylvania Holds Pay-If-Paid Clause Unenforceable Where Prime Contractor’s Inadvertent Delays Contribute to the...

Troutman Pepper on

Connelly Constr. Corp. v. Travelers Cas. & Surety Co. of Am., 2018 U.S. Dist. LEXIS 123009 (E.D. Pa. July 24, 2018). The Commonwealth of Pennsylvania Department of General Services undertook a project for the construction...more

Troutman Pepper

Claimant Is Not Required To Conduct An Investigation Into The Veracity Of The Representation To Prove Justifiable Reliance When...

Troutman Pepper on

Fisk Elec. Co. v. DQSI, L.L.C., 2018 U.S. App. LEXIS 17914 (5th Cir., June 29, 2018) - DQSI, L.L.C., (“DQSI”) a general contractor, was hired by the Army Corps of Engineers (“Corps”) for a pump station construction...more

Hogan Lovells

How to draft for concurrent delay wherever your projects are

Hogan Lovells on

A new English Court of Appeal decision shows how to allocate concurrent delay risk successfully. Our worldwide construction team helps your drafting reflect this growing tendency for courts and arbitrators globally to prefer...more

Bracewell LLP

Does the Prevention doctrine thwart contractually allocated Concurrent Delay risk? The English Court of Appeal says not

Bracewell LLP on

Energy sector participants will be familiar with the law of physics that states energy is neither created nor destroyed but can be converted from one form into another. Fossil fuels in the ground contain chemical energy and...more

Troutman Pepper

Federal Court in California Holds That Subcontractor May Proceed With Claim for Delay Damages, Despite No-Damage-For-Delay Clause,...

Troutman Pepper on

Rai Indus. Fabricators, LLC v. Fed. Ins. Co., 2018 U.S. Dist. LEXIS 74612 (N.D. Cal., May 2, 2018) - Sauer Incorporated (“Sauer”) contracted with the U.S. Army to design and construct the Operational Readiness Training...more

Troutman Pepper

Under Louisiana Payment Act, Once Contractor Meets Contractual Requirements for Final Payment, Public Entity Has a Duty to Issue...

Troutman Pepper on

Woodrow Wilson Constr. LLC v. Orleans Par. Sch. Bd., 2018 La. App. LEXIS 762 (April 18, 2018) - The Orleans Parish School Board (“OPSB”) awarded a prime contract to Woodrow Wilson Construction (“WWC”) for the construction...more

Bradley Arant Boult Cummings LLP

Be Aware of Sovereign Immunity - Construction and Procurement Law News, Q1 2018

Sovereign immunity is the legal doctrine, dating back to the days of the British monarchy, that a sovereign or state cannot commit a legal wrong and is immune from suit: in essence, “the king can do no wrong.” ...more

Troutman Pepper

Divided New York Court Of Appeals Holds That A Third Party Cannot Sue For Breach Of Contract Absent Express Language Naming Them...

Troutman Pepper on

Dormitory Auth. of the State of NY v. Samson Constr. Co., 2018 N.Y. Lexis 218 (February 15, 2018) - The Dormitory Authority of the State of New York (“DASNY”) undertook, as project manager, to construct a facility for the...more

Troutman Pepper

Michigan Court Of Appeals Holds That Contractor Who Failed To Timely Seek A Time Extension Is Barred From Contesting Liquidated...

Troutman Pepper on

Abhe & Svboda, Inc. v. State of Michigan Department of Transportation, 2017 Mich. App. Lexis 1387 (August 29, 2017) - Contractor Abhe & Svboda, Inc. (“A&B”) entered into a contract with the Michigan Department of...more

Snell & Wilmer

Pacing in Construction Scheduling Disputes

Snell & Wilmer on

On a high level, construction delay litigation involves sorting out the impacts to the critical project path and determining which party is responsible for those impacts. One of the more difficult elements of this process is...more

Troutman Pepper

Kentucky Appellate Court Holds That a Contractor May Pursue Claim of Negligent Misrepresentation Against Architect Despite Lack of...

Troutman Pepper on

D.W. Wilburn, Inc. v. K. Norman Berry Assocs., No. 2015-CA-001254-MR, 2016 Ky. App. Lexis 206 (Ky. Ct. App. Dec. 22, 2016) - This case arose out of a construction project in which the Oldham County Board of Education...more

25 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide