In NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), 2024 WL 1270188 (2d Cir. Mar. 26, 2024), the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s grant of summary judgment dismissing a...more
My commute home last night took longer than usual. It was not excessive traffic, an accident, or a stalled car. Rather, the cause of my delayed commute was a turtle: one single turtle crossing the road, holding up about 30...more
A common clause in many New York construction contracts is a “no-damage-for-delay” exculpatory provision, providing, in sum, that delay damages are not compensable and that if you are delayed, then you are only entitled to a...more
In this webinar series, George Pallas and Kathleen Morley present practical tips and training to project managers and supervisors regarding best practices in project management. Using real-life examples, George and Kathleen...more
In this webinar series, George Pallas and Kathleen Morley will present practical tips and training to project managers and supervisors regarding best practices in project management. Using real-life examples, George and...more
It happens all the time! The owner-contractor agreement contains a “no damages for delay” clause; a clause requiring that all changes be in writing before work is performed; and a clause requiring partial lien waivers and...more
Construction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays...more
Rad and D’Aprile, Inc. v. Arnell Construction Corp, No. 502464/14, 2019 BL 131606 (NY. Sup. Ct. April 3, 2019) - In June of 2001, Arnell Construction Corp. (“Arnell”) entered into a prime contract to build two sanitation...more
Rai Indus. Fabricators, LLC v. Fed. Ins. Co., 2018 U.S. Dist. LEXIS 74612 (N.D. Cal., May 2, 2018) - Sauer Incorporated (“Sauer”) contracted with the U.S. Army to design and construct the Operational Readiness Training...more
No-damages-for-delay clauses are commonly found in construction contracts and, with certain exceptions, are generally recognized as valid and enforceable. The exact language can vary, but the typical clause provides that the...more
The United States Department of Veterans Affairs (the “VA”) contracted with Sygnos, Inc. (“Sygnos”) for improvements to the electrical system at a VA hospital in Boise, Idaho. Sygnos subcontracted a portion of the work to...more
Whether you are an owner, contractor, subcontractor or supplier, you will want to read the rest of this post since it illustrates precisely what all those attorneys have been telling you for years: “Please, please, please...more