Identifying and Quantifying Government Contract Claims
Practical Training for Project Managers & Supervisors Two-Part Webinar Series: Part Two
In NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), 2024 WL 1270188 (2d Cir. Mar. 26, 2024), the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s grant of summary judgment dismissing a...more
In WDF, Inc. v. City of New York, No. 652478 (N.Y. Sup.) (Mar. 12, 2021), the contractor filed suit to recover damages from the City on numerous combined waste water treatment projects. The contractor claimed that the City...more
It happens all the time! The owner-contractor agreement contains a “no damages for delay” clause; a clause requiring that all changes be in writing before work is performed; and a clause requiring partial lien waivers and...more
If you are left in the dark about something, you don’t have the information you should have to make an informed decision. Delay claims on a construction can be confusing, especially when you think about the delay to the work...more
D.A. Nolt, Inc. v. The Philadelphia Municipal Authority, 2020 BL 199761 (E.D. Pa. May 28, 2020) - The Philadelphia Municipal Authority (the “Authority”) contracted D.A. Nolt, Inc. (“Nolt”) to renovate a building that would...more
Construction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays...more
It almost goes without saying that if you have to pursue or defend a delay claim, you are going to need some evidence (preferably by an expert) to establish or to challenge entitlement to the damages sought. And we all know...more
Connelly Constr. Corp. v. Travelers Cas. & Surety Co. of Am., 2018 U.S. Dist. LEXIS 123009 (E.D. Pa. July 24, 2018). The Commonwealth of Pennsylvania Department of General Services undertook a project for the construction...more
A new English Court of Appeal decision shows how to allocate concurrent delay risk successfully. Our worldwide construction team helps your drafting reflect this growing tendency for courts and arbitrators globally to prefer...more
Dormitory Auth. of the State of NY v. Samson Constr. Co., 2018 N.Y. Lexis 218 (February 15, 2018) - The Dormitory Authority of the State of New York (“DASNY”) undertook, as project manager, to construct a facility for the...more