Third Circuit Upholds PJM Capacity Market Change but Prevents Retroactive Application

Troutman Pepper on

On March 12, 2024, the U.S. Court of Appeals for the Third Circuit upheld a prospective rule change to PJM Interconnection, L.L.C.’s (“PJM”) annual capacity auction but struck down attempts by PJM and FERC to apply the rule...more

Paul Hastings LLP

FERC Proposes Rule to Prohibit Reactive Power Compensation for Generators

Paul Hastings LLP on

On March 21, 2024, the Federal Energy Regulatory Commission (FERC or Commission) issued a Notice of Proposed Rulemaking (NOPR) in Docket No. RM22-2 that proposes to prohibit transmission providers from allowing generating...more

Troutman Pepper

D.C. Circuit Upholds PJM Tariff Changes to Planning of Asset Management and End of Life Projects

Troutman Pepper on

On November 17, 2023, the U.S. Court of Appeals of the District of Columbia Circuit (“D.C. Circuit”) denied petitions challenging FERC’s approval of recent changes to the PJM Interconnection, L.L.C.’s (“PJM”) Open Access...more

Troutman Pepper

PJM Files Capacity Market Overhaul for Resource Adequacy and Grid Reliability

Troutman Pepper on

On October 13, 2023, PJM Interconnection, L.L.C. (“PJM”) submitted two filings with FERC proposing revisions to its Open Access Transmission Tariff (“Tariff”) and its “Reliability Assurance Agreement” (“RAA”) designed to...more

Orrick, Herrington & Sutcliffe LLP

FERC Approves PJM Interconnection Process Reforms to Address Backlog

On November 29, 2022, FERC issued an order approving a proposal by PJM to reform its interconnection procedures to enable it to process new interconnection requests more efficiently. The PJM reforms represent one of several...more

Stoel Rives LLP

FERC Accepts PJM’s Interconnection Queue Reform

Stoel Rives LLP on

In a “FERC after dark” order issued late yesterday, November 29, the Federal Energy Regulatory Commission (FERC) largely accepted a comprehensive reform of the PJM interconnection process that applies to both generation and...more

A&O Shearman

PJM Makes MOPR Compliance Filing and Proposes Timing for Delayed RPM Auction

A&O Shearman on

Ohio Commission Requests Comment Delay for COVID-19 Emergency On March 18, PJM Interconnection, L.L.C (PJM) filed with the Federal Energy Regulatory Commission (FERC) proposed changes to its Tariff in compliance with FERC’s...more

King & Spalding

Impact of the Delayed PJM Base Residual Auction on Excess Cash Flow Sweeps Under Construction Financings

King & Spalding on

In a July 25, 2019 order, the Federal Energy Regulatory Commission (“FERC”) directed PJM Interconnection, L.L.C. (“PJM”) not to conduct the Base Residual Auction (“BRA”) to procure capacity for the 2022-2023 delivery year in...more

Akin Gump Strauss Hauer & Feld LLP

FERC Orders on PJM’s Frequency Regulation Market Give Energy Storage Providers Another Recent Win

On March 30, 2018, the Federal Energy Regulatory Commission (FERC or the “Commission”) issued separate orders (i) partially granting one of two challenges to PJM Interconnection, L.L.C.’s (PJM) frequency regulation...more

9 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide