CPUC Seeks Comments on Centralized Procurement Mechanism Impacting California Offshore Wind Development

On April 26, 2024, Administrative Law Judge Julie Fitch of the California Public Utilities Commission (CPUC) issued a ruling seeking comments on the use and implementation of a centralized procurement mechanism established in...more

Perkins Coie

Floating Offshore Wind in the Gulf of Maine—BOEM and the State of Maine Take Next Steps Toward Development and Procurement of...

Perkins Coie on

Marching toward its goal of deploying 30 gigawatts (GW) of offshore wind by 2030, the Bureau of Ocean Energy Management (BOEM) published on May 1, 2024, a proposed sale notice (PSN) to auction eight lease areas for commercial...more

Latham & Watkins LLP

BOEM Floats Proposal to Modernize Offshore Wind Regulations

Latham & Watkins LLP on

A new proposal aims to streamline the process for permitting and developing offshore renewable energy projects and reduce costs to developers. On January 30, 2023, the Bureau of Ocean Energy Management (BOEM) published a...more

Bricker Graydon LLP

Attention Ohio energy developers: Ohio Power Siting Board issues proposed rule revisions

Bricker Graydon LLP on

On June 16, 2022, the Ohio Power Siting Board (“Board” or “OPSB”) issued a comprehensive set of proposed revisions to the rules governing the procedures before the OPSB and its siting criteria. The Order culminates a...more

Downey Brand LLP

California Offshore Wind Gains Momentum with Two Key Milestones in April

Downey Brand LLP on

In early April there were two major leaps forward in offshore wind development in California. On April 6, 2022, the Bureau of Ocean Energy Management (BOEM), a bureau within the U.S. Interior Department, released a Draft...more

Bennett Jones LLP

Canada's Clean Electricity Standard Consultation Underway

Bennett Jones LLP on

The Government of Canada (through Environment and Climate Change Canada) launched a consultation through the publication of a discussion paper, "A Clean Electricity Standard in support of a net-zero electricity sector:...more

Akin Gump Strauss Hauer & Feld LLP

PURPA Dispute at FERC Raises New Questions for Co-Located Energy Storage

On August 31, 2018, NorthWestern Corporation (NorthWestern) petitioned the Federal Energy Regulatory Commission (FERC or Commission) to revoke the qualifying small power production facility (QF) status of four wind projects...more

Pierce Atwood LLP

Maine DEP Developing New Rule For Wind Power Projects

Pierce Atwood LLP on

The Maine Department of Environmental Protection has announced that it is developing a new Site Law rule that will address certain development standards for wind projects. The standards that will be addressed by the new rule...more

Stinson LLP

Streamlining the Siting of Transmission in the West - Why Transmission and Renewable Energy Project Developers Should Care About...

Stinson LLP on

Early this month, the Department of Energy (DOE) issued notice (81 FR 5283) of a proposed rule aimed at streamlining the pre-application process for transmission developers to obtain federal authorization to construct and...more

Parker Poe Adams & Bernstein LLP

American Wind Energy Association Seeks Revisions to Generator Interconnection Rules

On June 19, 2015, the American Wind Energy Association (“AWEA”) filed a petition with the Federal Energy Regulatory Commission (“FERC”) for a rulemaking to revise the FERC’s pro forma Large Generator Interconnection...more

10 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide