Timing Matters for Differing Site Conditions

Gray Reed on

Many construction contracts contain some version of a “differing site conditions” clause. AIA’s A201 general conditions, as well as in the EJCDC equivalent, contains a changed site condition clause. It also appears in most...more

Troutman Pepper

Evidence That Government Internally Considered Additional Modifications After the Parties Had Signed Earlier Modifications May...

Troutman Pepper on

Meridian Eng’g Co. v. United States, 2018 U.S. App. LEXIS 7024 (Fed. Cir., Mar. 20, 2018) - Meridian Engineering Company (“Meridian”) was hired by the United States (“Government”) to construct flood control structures on...more

Gray Reed

When is an Unforeseen Condition a “Differing Site Condition”?

Gray Reed on

Many construction contracts contain some version of a “differing site conditions” clause. It is found in the current version of AIA’s A201 general conditions, as well as in the EJCDC equivalent. It also appears in most...more

Baker Donelson

Finally - A Different Result for a Government Contractor's Differing Site Condition Claim

Baker Donelson on

For any government contractor that has had a differing site condition claim denied despite relying on a government geotechnical report about the subsurface conditions of the project site, the U.S. Court of Appeals for the...more

4 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide