Generator Interconnection Rule: FERC Provides Clarification and Tweaks to Order No. 2023 But Stands Firm on Late Study Penalties

Husch Blackwell LLP on

On March 21, 2024, FERC issued a follow up rehearing order to its landmark Order No. 2023 generator interconnection reform rule, providing several clarifications and tweaks in response to industry comments. Improvements to...more

Vinson & Elkins LLP

Improvements to Generator Interconnection Procedures and Agreements

Vinson & Elkins LLP on

On July 27, 2023, the Federal Energy Regulatory Commission (“FERC” or the “Commission”) issued a final rule intended to revolutionize the interconnection process. Among other things, the final rule replaces the prior...more

2 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide