FERC May 2024 Open Meeting Preview

Foley Hoag LLP on

It’s a busy time for the Federal Energy Regulatory Commission (the “Commission” or “FERC”). In March 2024, FERC issued Order No. 2023-A upholding its major generator interconnection reform order, Order No. 2023. FERC followed...more

Husch Blackwell LLP

FERC's Generator Interconnection Queue Reform Makes Welcome Improvements, but the Devil Will Be in the Details of the Compliance...

Husch Blackwell LLP on

On July 28, 2023, the Federal Energy Regulatory Commission (FERC) issued a landmark order that reforms the generator interconnection process in response to a clear need for nation-wide improvements due to rapidly changing...more

Alston & Bird

FERC Issues Rehearing Order on Reform of Large Generator Interconnection Procedures and Agreements

Alston & Bird on

Our Energy Group examines the Federal Energy Regulatory Commission’s Order No. 845-A and what it means for the large generator interconnection industry....more

Orrick, Herrington & Sutcliffe LLP

FERC Proposes Broad Changes to Its Pro Forma Interconnection Procedures and Interconnection Agreement

In its final meeting of 2016, FERC issued a notice of proposed rulemaking in which it proposes changes to its standard interconnection rules and agreement for generators with a capacity of more than 20 megawatts. The proposed...more

4 Results
 / 
View per page
Page: of 1

"My best business intelligence, in one easy email…"

Your first step to building a free, personalized, morning email brief covering pertinent authors and topics on JD Supra:
*By using the service, you signify your acceptance of JD Supra's Privacy Policy.
- hide
- hide